大发888官方指定下载网址,dafa888官网开户,大发888官方网站

Copper base alloy and superalloy material construction project -- secondary publicity

发布时间:2019-10-15   阅读次数:141

     1.Name and summary of the construction project

     ⑴Project name: Copper-based alloy and high-temperature alloy material construction project

     ⑵Construction unit: Shaanxi Sirui Advanced Materials Co., Ltd.

     ⑶ Construction site: No. 12 Zhang Ba Qi Road, High-tech Zone, Xi'an

     ⑷ Construction nature: technological transformation and others

     ⑸Total investment: 200 million yuan

     ⑹ Construction content: the reconstruction and expansion project to purchase a total of 287 sets of hardware equipment , will be the vacuum casting   

     copper chromium alloy material expansion and chromium zirconium copper alloy material industrialization construction project equipment for renewal,  

     improve material performance and processing accuracy, so as to improve product quality, expand production capacity, broaden the product field.

     2.Basic information of construction company

     Construction company: Shaanxi Sirui Advanced Materials Co., Ltd.                                                              Contact: Fei Gaiyun

     Construction address: No. 12 Zhang Ba Qi Road, High-tech Zone, Xi'an                                                      Contact number: 18691893038

     3.Basic information of environmental impact assessment company

          company Name: Shaanxi Zhongkeruisi Environmental Protection Technology Co., Ltd.

          Contact: Song Nan                                                                      Contact number: 18591088715

     4.Access to public comment forms and environmental Assessment reports (draft)

     1. Environmental Impact Report (draft)

     See Annex 1 for details of environmental Impact Report of Copper base Alloy and Superalloy Material Construction Project (Draft).

     2. Public opinion form

     See Annex 2 for the Public Opinion Form on Environmental Impact Assessment of Construction Projects.

     Paper report access: the public can go to Shaanxi Sirui Advanced Material Co., LTD.

     Public Posting place: Shaanxi Sirui New Advanced Co., LTD.

     5.Main issues for public comment

     The public scope for comment is mainly the residents near the project, and the main items include your suggestions and requirements for the environmental protection of the project, etc.

     6..  Ways for the public to put forward opinions

     You can use any of the following methods to feedback your comments to us:

     1. Dial the contact number.

     2. By letter, fax, e-mail.

     3. Fill in the public comment form.

     7.The start and end time for public comments

     The publicity period is 10 working days. During the publicity period, the public who has objections, questions or suggestions on the construction of the project can contact the construction company, the eia company and the competent department to put forward opinions or suggestions.

                                                                                                                                                                                                                                                                                                                                                                                          Shaanxi Sirui Advanced Materials Co., Ltd.          

                                                                                                                                                                                                                                                                                                                                                                                                                    2019-10-15                

     Attachment:

     “Environmental Impact Report of Copper-based Alloy and Superalloy Material Construction Project (Draft for Solicitation of Comments)"

     "Public Opinion Form for Environmental Impact Assessment of Construction Projects"